VECTREN

Current Campaigns

Related Documents

April 26, 2017

Vectren Rate Case Fact Sheet

August 25, 2016

Average Vectren Bill PDF

In the Media

October 30, 2015

The Indiana Court of Appeals yesterday struck down approval of Vectren’s plan to spend roughly $90 million in ratepayer money on its aging A.B. Brown and F.B. Culley coal-fired power plants outside Evansville. The Court found that the Indiana Utility Regulatory Commission violated the law by failing to determine whether Vectren met all legal requirements before approving Vectren’s use of the new equipment. The Court’s decision means that the case goes back to the Commission to decide whether Vectren should be allowed to pass the costs of the projects on to its ratepayers.

November 19, 2012

The Indianapolis Star's Tony Cook shed some light on Vectren's questionable tactic of buying high-priced coal from its own subsidiary.  

"Residents of southwest Indiana long have grumbled about high electricity bills, and for good reason -- they pay the highest rates in the state.